Akufo-Addo inspects ongoing Mumford Landing Site

The President of the Republic, Nana Addo Dankwa Akufo-Addo, on Friday, paid a working visit to Mumford to inspect the ongoing Landing site to ascertain the progress of work done so far.

The Mumford Landing Site project commenced on November 16, 2019.

With the topographic and geophysical surveys one hundred percent (100%) complete, and work on the breakwater is seventy percent (70%) complete, prefabrication of the concrete blocks for the quay wall begins in September 2020, with dredging work for the approach channel and port basin starting in December.

According to the Minister for Transport, Kwaku Ofori Asiamah, the Mumford landing site will be completed in June 2021, and will have the following facilities also attached to the site: an administration building, fish market, net mending hall, ice making plant, fuel depot, day care centre, toilet, and power station.